The UK’s electricity transmission and distribution systems have little spare capacity to accommodate the widespread changes in volume and location of power flows arising from planned changes in generation type and characteristics, and from major changes in demand patterns. Gaining consents for the construction of new overhead lines is extremely time-consuming and costly. Without action, this will increasingly constrain the necessary changes in generation and demand.
The ‘Network Capacity’ project has assessed the feasibility of using new technologies now emerging in the marketplace or in development, including multi-terminal HVDC systems, in novel ways in order to provide increased Transmission & Distribution system capacity and improved management of network power flows, in order to facilitate increased renewable energy installation levels in the UK.
This document addresses the full range of technologies considered during the project, including both FACTS and HVDC technologies. It contains two reports:Appendix A. Smarter Grid Solutions Report: Technology Options, Benefits and Barriers Workshop Review (Task 6; starts page 11)
The main objectives of the workshop were to:Ensure all participants are informed about project activities and expected outcomesConsider the relative merits of the technologies under reviewIdentify all issues that translate into benefits or barriers for the technologies under reviewIdentify and prioritise assessment criteriaAssess the range of opinions on uncertain, controversial and subjective issues•Identify and assess technology development opportunitiesThe workshop satisfied all of these objectives
Appendix B. Smarter Grid Solutions Report: Multi-Criteria Assessment of Technologies (Task 7; starts page 42)
This workshop looked at the interaction between various factors in selecting the most appropriate area of further investigation.The assessment results indicated that the assessment criteria would be fulfilled most effectively by pursuing the following development options:
Investigate use of energy storage to help solve ANM constraintsCommission work on new HVDC systems/topologiesPrompt changes in regulatory framework to change business driversDevelop effective DC breaker or blocking capabilityAn alternative interpretation of the analysis is to focus on the one criterion that was ranked most highly, which was the potential to reduce CO2 emissions.The development options that were co...
The ‘Network Capacity’ project has assessed the feasibility of using new technologies now emerging in the marketplace or in development, including multi-terminal HVDC systems, in novel ways in order to provide increased Transmission & Distribution system capacity and improved management of network power flows, in order to facilitate increased renewable energy installation levels in the UK.
This document addresses the full range of technologies considered during the project, including both FACTS and HVDC technologies. It contains two reports:Appendix A. Smarter Grid Solutions Report: Technology Options, Benefits and Barriers Workshop Review (Task 6; starts page 11)
The main objectives of the workshop were to:Ensure all participants are informed about project activities and expected outcomesConsider the relative merits of the technologies under reviewIdentify all issues that translate into benefits or barriers for the technologies under reviewIdentify and prioritise assessment criteriaAssess the range of opinions on uncertain, controversial and subjective issues•Identify and assess technology development opportunitiesThe workshop satisfied all of these objectives
Appendix B. Smarter Grid Solutions Report: Multi-Criteria Assessment of Technologies (Task 7; starts page 42)
This workshop looked at the interaction between various factors in selecting the most appropriate area of further investigation.The assessment results indicated that the assessment criteria would be fulfilled most effectively by pursuing the following development options:
Investigate use of energy storage to help solve ANM constraintsCommission work on new HVDC systems/topologiesPrompt changes in regulatory framework to change business driversDevelop effective DC breaker or blocking capabilityAn alternative interpretation of the analysis is to focus on the one criterion that was ranked most highly, which was the potential to reduce CO2 emissions.The development options that were co...